Central Expressway
By Thulaja, Naidu Ratnala written on 2003-11-27
National Library Board Singapore
Comments on article: InfopediaTalk
Central Expressway (CTE) connects the
Seletar Expressway (SLE) at its junction with the Tampines
Expressway (TPE) in the north to the Ayer Rajah Expressway
(AYE) in the south near its junction with the East Coast
Parkway (ECP). It links the north and the south of Singapore
through the Central Business District (CBD). Constructed in two
phases, the CTE opened in 1991. Portions of the road are laid
underground and these parts of the CTE form the first
underground highways of Singapore.
History
The CTE, a 16 km expressway, was constructed at a total cost of
S$500 million. It was built in two phases with different stages
that involved a total of eleven parts or sections of
construction. The laying of the 12.5 km stretch of road from
Yio Chu Kang to Bukit Timah Road formed phase one of the
construction, which was completed in the 1980s. The portion of
expressway between Yio Chu Kang and Ang Mo Kio Avenue 5 was
officially opened on 17 June 1989 by the Member of Parliament
for Cheng San GRC, Heng Chiang Meng. The construction of this
1.7 km three-lane carriageway stretch of the expressway was
delayed by almost two years due to resettlement problems when
residents in the area had to be moved. The first phase of the
expressway construction also included the building of the
Whampoa flyover connecting the Pan-Island Expressway (PIE) and
CTE.
The Public Works Department began accepting tenders for the
construction of the 3.7 km phase two of the CTE in April 1986.
Dubbed the city portion project of CTE, PWD engineers took more
than two years in finalising the plan for this phase before
requesting for tenders. It was not only touted as the single
most expensive road project of Singapore at that time because
of the construction of two underground tunnel ways, but was
also considered a complicated and difficult road to lay because
of its design. From more than ten civil engineering firms that
pre-qualified for the job and eight short-listed candidates,
contracts for the construction of various jobs in this phase
were awarded to a group comprising of the firms, Bocotra
Construction, Lee Kim Tah, Metrobilt and Wang Coo Kien.
Construction of the road commenced on 25 January 1988 and
excavation work for the underground tunnels began in June 1988.
The government acquired nearly 54,000 sq m of land around the
areas of Orchard Road, Cavenagh Road and Clemenceau Avenue for
the project, after first earmarking the areas in 1986. The
total cost of the phase two of the construction was S$350
million.
As a part of the 1990's PIE widening project, the Whampoa
flyover was improved to become the only four-way junction for
intersecting expressways in Singapore. On completion of the
improvement work, this flyover was officially opened by Acting
National Development Minister Lim Hng Kiang on 29 October
1994.
Underground tunnels
Of the total 3.7 km of CTE from Bukit Timah Road to Chin Swee
Road, only about 1.3 km of the expressway form the surface
roads, including parts of which were constructed below existing
road levels. The rest of the expressway is laid underground.
There are two tunnels: north and south. The north tunnel is a
41 m wide, 700 m stretch of road from the junction of Bukit
Timah and Cavenagh Road to the junction of Clemenceau Avenue
and Cairnhill Circle. This portion of the expressway is divided
into northern and southern carriageways with four lanes each.
An interchange was built at Clemenceau avenue to allow
motorists to have access to Orchard Road by driving off the CTE
up Cairnhill Circle and into Orchard Road. Due to the existence
of the interchange, both Cairnhill Circle and Bideford Road
were converted into one-way lanes on completion of the
construction of the CTE.
The south tunnel extends from under the Meridien Orchard Hotel
in Orchard Road to Chin Swee Road. Measuring a total of 1.7 km,
it passes below Penang Road, Singapore River and Havelock Road.
It has three lanes on its either side. The portion of the
tunnel under water is near the Clemenceau Bridge over the
Singapore River. At this point the expressway lies two metres
under the Singapore River. Stones were laid over the river bed
to prevent the river from eroding to the tunnel level. This
section of the expressway took almost two years to build as the
river had to be dammed in stages during the construction. The
south tunnel was considered the toughest part of the entire CTE
to build because of its tricky layout. A portion of the
expressway even cuts across an MRT tunnel between Somerset and
Dhoby Ghaut MRT stations. It also cuts across the Stamford
Canal near the Kramat Lane. A three storey interchange, with
five slip tunnels, links the expressway with some of the
surface roads here such as the Merchant Road, Havelock Road and
Upper Cross Street.
Construction work
Because of a variety of soils along the route, more than six
different types of temporary retaining walls were put up during
the excavation and tunnel building work. As the diameter of the
tunnels are around three to four times of MRT tunnels, their
large size made it necessary to use the cut-and-cover method
for most part of their construction, instead of the boring
method used in the building of the MRT tunnels. Traffic was
diverted along the excavation sites resulting in the loss of
two to three lanes along major traffic routes. Instruments were
attached to around 40 buildings that came within 50 m of the
excavation sites to monitor noise and vibration levels. Some of
the buildings in this category include Meridien Orchard Hotel,
Landmark Tower, Thong Chai Building, Central Building, Liang
Court, Singapore Shopping Centre, Glass Tower and some HDB
housing units. Around 440,000 cu m or 70,300 truckloads of
concrete was used for the entire second phase of the
construction.
The construction of the last section of the CTE was completed
in April 1991. A mass walk-and-jog event was held on 15
September 1991 for people to familiarise themselves with the
tunnels a week before the official opening of the CTE. More
than 10,000 turned up for the event, which was a seven km route
covering both tunnels and their surface connections. The event
was flagged off by the Senior Parliamentary Secretary for
National Development Lee Yiok Seng. The official opening
ceremony of the CTE's second phase took place on 21
September 1991. The tunnels were opened to traffic at 6 pm
and about 50 vintage cars, led the procession with the Senior
Minister of State Tay Eng Soon at its head in a 1935 BMW. They
became the first motorists to use this portion of the
CTE.
Description
The concrete roof of the tunnels are 1.5 m thick. The
shallowest part of the tunnel is 1.5 m below the ground while
the deepest part of the tunnel is five to six metres below the
ground. Fire protection, emergency power supply systems,
hi-tech gadgetry to ensure safety and sophisticated traffic
surveillance and control, all add up to the maintenance cost of
four to five million dollars for the tunnels annually.
Detectors have also been installed to warn of congestion should
lanes close for reasons such as a traffic accident. Ventilation
is automatically adjusted according to the volume of the
traffic. Lighting in the tunnels is automatically adjusted too.
Staircases leading to the ground level are located at every 200
m interval. Closed-circuit television cameras are installed
every 100 m while hydrants, hose reels and fire extinguishers
are located at every 50 m interval. Everything in the tunnel is
monitored from the computerised 24 hours tunnel control
centre.
Significant construction along the CTE include private and HDB
housing units, the Ang Mo Kio ITE, Da Qiao Primary School,
Singapore Cheshire Home and Serangoon Garden Estate. The Chong
Li Primary School and Chong Boon Secondary School are located
in a common compound near the Ang Mo Kio Central Flyover Park
at the junction of Ang Mo Kio Avenue 3 and the CTE. Significant
construction along the expressway also includes the Ang Mo Kio
Industrial Park, Construction Industry Training Institute, Toh
Payoh Industrial Park, Volkswagen Golf Centre, St. Andrew's
Secondary School with the Chapel of the Holy Spirit next to it,
St. Wilfred Field, Bendemeer Secondary School, ITE Balestier
and the Seventh Day Adventist Church with the Eye Hospital next
to it. The CTE runs below a number of popular landmarks in the
CBD, such as the Istana Park. Vehicular bridges have been
constructed over the Kallang River and Sungei Whampoa.
Author
Naidu Ratnala Thulaja
References
Bidding date for Central Expressway extended. (1987, May 20).
The Straits Times.
Central expressway project progressing well despite problems.
(1989, June 2). The Business Times, p. 1.
CTE project completed. (1991, May 11). The Straits
Times, p. 22.
CTE project uses 5,000 truckloads of concrete each month (1989,
December 16). The Straits Times, p. 24.
CTE stretch at Ang Mo Kio now open. (1989, June 18). The
Straits Times, p. 16.
Dhaliwal. R. (1988, September 28). Work starts on Central
Expressway tunnels. The Straits Times. p. 18.
Dhaliwal, R. (1989, February 25). Move to speed up work on the
CTE . The Straits Times, p. 24.
Inside Singapore's massive road project. (1988, March 04).
New Straits Times, p. 14.
Lee, H. S. (1988, March 02). Work starts soon on underground
highway. The Business Times, p. 18.
Kumar, S. (1991, January 04). CTE tunnels ready before
year's end. The Business Times, p. 24.
10,000 throng CTE tunnel for jog and walk. (1991, September
16). The Straits Times, p. 1.
Pereira, M. (1989, January 09). CTE at 'critical stage'
as excavation work starts. The Straits Times. p.
13.
Underground CTE to open on Sept 21. (1991, August 8). The
Straits Times, p. 1.
Vintage cars in drive for funds to be first to use tunnels.
(1991, September 20). The Straits Times, p. 26.
Work begins to put finishing touches to some parts of CTE.
(1990, June 2). The Straits Times, p. 22.
Work on CTE tunnel roads begins. (1988, July 18). The
Business Times, p. 20.
Work on the Central Expressway Phase 2. (1989, September 1).
The Business Times, p. 2.
Yap, M. (1986, April 18). Tenders open for phase two of CTE.
The Straits Times.
Bachy Soletanche Singapore Pte Ltd. (n.d.). 2000 -
CTE/Braddell Road Interchange diaphragm wall. Retrieved
December 16, 2003, from
www.bachy-soletanche.com.sg/bss-thumbs/055-braddell/BSS-055-BraddellRd.htm
The information in this article is valid as at 2003 and correct
as far as we can ascertain from our sources. It is not intended
to be an exhaustive or complete history of the subject. Please
contact the Library for further reading materials on the topic.
Subject
Commerce and Industry>>Transportation
Express highways--Singapore
Science and technology>>Engineering>>Transportation engineering
All Rights Reserved. National Library Board Singapore 2004.